BPR is a tool for significant change in organisation performance.
Adjusting the thinking which has led to the current situation is the greater priority. A
change of the order achieved by BPR is, de facto, a major change to the system. It will be
argued that the opportunity exploited by BPR has, in part, been created by the way we
currently think about and run our organisations.
It is thinking that informs culture - the way people in organisations
behave - and success or failure with BPR has already been shown to be dependent on
organisational culture.
Juran said all there was to say in his book Managerial Breakthrough, there
being only two ways of improving performance - reducing variation and redesign. BPR is
redesign of a more extraordinary nature than he could have imagined. Managers still show
little understanding of the principle of variation and that failing is just part of the
wider problem - managerial thinking - which underpins success or failure with BPR.
Two important changes have occurred since Juran wrote about performance
improvement. Firstly, he could not have predicted the impact of information technology
(IT) on organisations, secondly, he wrote in the socio-cultural context of his time when
there was more of a gulf between managers and workers. IT is sometimes an important
enabler of organisation change (but no more than that). It is the socio-cultural issues
that have been and continue to be the dominant issues in transforming organisations. There
have been outstanding examples of performance improvement with BPR. At the same time there
are many examples of disappointment and failure. Organisation culture has been identified
as a key determinant of success or failure. Here we address two cultural issues; the
thinking about the initiative itself and implementing changes as a consequence of the
initiative.
Thinking about the initiative - why are we doing BPR?
Following fashion?
Though they would not be proud to confess it, there are organisations
which have undertaken BPR simply because it seemed to be the thing to do.
In one case, a BPR project team had successfully collapsed a number of
processes into one, providing customers with a better quality service. The project had
been completed in one branch when top management took a more active interest. What, they
asked, would be the manpower savings if this change were rolled-out to all branches? The
project team couldnt answer. It had not originally been their intention to reduce staff
numbers, neither had they conducted any pre and post productivity measurement. Top
management had endorsed the project because it was something everyone was doing and it
fitted with their general desire to improve service. Later they saw it as a potential
opportunity to satisfy a different agenda.
Can costs be reduced through BPR? Of course. But if BPR is approached with
a cost-cutting mentality we run the risk of diminishing its potential value.
Re-engineering or cherry picking?
A utility company employed consultants to lead an internal BPR project
team. The brief was to re-engineer customer acquisition and customer service processes.
The team were guided through a process mapping methodology which they then applied. They
were told to identify opportunities for improvement and make recommendations to the top
management team. More than seventy recommendations were made. Top management chose to
implement only some of the recommendations, those that they felt would achieve the best
cost savings. Members of the project team were disappointed, they felt they had not
explained themselves well enough. They knew that many of their recommendations could not
be cherry-picked - they had to be seen as interdependent.
Top management needed to be influenced to see their organisation as a
system. That's a difficult task for their subordinates. If they had taken such a
perspective they would have seen the interdependencies (they would also have been in a
better position from which to choose priorities).
Improving service?
A customer-service organisation employed IT consultants to re-engineer
their front and back offices. The consultants set themselves up in a room in the client's
building. They brought with them computer applications which would map the current
processes. One by one staff were invited to the consultants' room to explain what they
did. The consultants recorded each individual's inputs, activity and outputs. The result
was a complex mapping of all current activity.
The consultants took a view on how the processes could work and what the
resulting improvements would be in service and efficiency. As a part of their presentation
(designed to sell the next tranche of work) they discussed the importance of managing
resistance to change. In fact, the consultants approach had already created it. The top
management had been lobbied by staff who felt the method was unacceptable. They had given
the consultants all of their thoughts about how the organisation worked and how it should
work. They felt that they had a stake in its future and were fearful of being manipulated.
The chief executive realised that the people were his most important asset. They should
not be subjected to change, they should be at the heart of it. As they developed
solutions, their knowledge would be an appreciating asset. The consultants were fired and
the organisation took a different route which put the staff at the centre of the action.
These cases are not unusual. Implicit in these experiences are assumptions
about the purpose and methods of change. Many of these assumptions are manifestations of
traditional management thinking - thinking which has stood in the way of change for
generations - BPR is merely the latest intervention to suffer in the hands of traditional
management; its failure is only further evidence that we have a more pressing problem. The
problem of management itself.
Traditional management thinking impedes effective change
In traditional command and control cultures, managers think about their
organisations as a collection of functions. Budgets are drawn up which set expectations
for functional or departmental performance. Viewed from such a perspective managers look
for opportunities to improve departmental numbers and change will tend to be a
cost-cutting or cherry-picking exercise which can ignore deleterious consequences in other
parts of the organisation. The organisation is not a mere collection of functions, it is a
system - the parts are interdependent, they work together for better or worse.
In many cases BPR is treated as a project. The project team is to do the
analysis and implement the required changes. However, if management thinking and behaviour
remains the same (attending to functional performance), the result is only a
re-arrangement of the original pathology. Learning is unlikely.
The organisation as a system
It was Deming(2) who observed that management's failure is a failure to
distinguish between costs and the causes of costs. Costs are easily identified in
financial reports, causes of costs are in the system and usually need to be found.
To illustrate: the teams in the second example had mapped the process for
handling invoice queries and recommended actions which would have reduced the number of
handovers and hence increased the efficiency of handling queries. Going straight to an
analysis of activity meant that they missed the wider perspective - over half of the
customers calling in with invoice queries abandoned their first call (it was difficult to
get through to credit control). These customers then called the sales offices who
processed their calls to credit control by filling in forms. The forms took six days to
get to someone who would respond to the customers, so customers called in again. The
volume of invoice queries was stifling the whole system. There was no study of what caused
invoice queries with a view to eradicating them. The recommendations were limited to what
each of the departments (finance and sales) could do to improve the current processes.
The real costs of operating this system were increased simply by the way
the system worked. The best way to improve sales revenue would have been to prevent
billing enquiries from clogging the sales process. This view was beyond the horizon of the
managers, whose view was framed by the numbers they worked with: in finance, bad debt; in
sales, time to answer, volume of calls unanswered and revenue. These numbers gave no
indication of the problems. BPR is less than successful when managers don't see their
organisation as a system.
Our organisations, run as traditional, command and control, hierarchical,
functional and output-driven systems have created many of the opportunities for BPR -
poor, inflexible service defines the need. The current situation can only be addressed by
radically re-thinking the way things are done.
In our experience, the adequacy of studies at the beginning of BPR work is
the single biggest weakness. People in organisations have been conditioned to look inward
and upward. Traditional specialisation of work breeds unresponsiveness to the external
environment. The whole thrust of BPR is to cut through the complicated processes built by
years of working with functional specialisation. The anchor required to pull through that
view lies outside the organisation - it is based on a clear understanding of what matters
to customers and our current capability in achieving it.
In the above example, a study of capability would have shown the
following:
ˇ fifty percent of customers with billing enquiries abandoned their call
ˇ of those that got through to credit control, only fifteen percent were
resolved at the first point of contact
ˇ forty percent of calls to sales offices were billing enquiries
ˇ the time taken to respond to queries that originated at the sales
offices was six days
ˇ customers who initiated their billing enquiry at a sales office were
likely to ring again to progress chase their call
All of these phenomena were predictable. If nothing happened they would
continue. What is the purpose of this system? To make it difficult for customers to
resolve their invoice queries?
A functional view or a system view?
That analysis teams and management decision-makers tend to focus inwardly
is, again, a reflection of an adherence to the functional view of organisations. The
finance, sales and service directors were all prone to adopt recommendations that made
sense to their particular function. Being responsible for their functional numbers, none
was inclined to take a broader view. Even if they'd had the inclination, they had amongst
them no experience of viewing and managing their organisation as a system. Such a
different view requires insight, creativity and judgement. It is a challenge simply
because it is unfamiliar territory for most managers.
How would understanding the organisation as a system help the manager with
BPR?
There are four levels of understanding:
Thinking
Purpose
Design
Method
BPR generally concentrates on design and method. Thinking, however is the
strongest lever for change as it impacts everything that follows.
What do we want from BPR?
Improved performance (revenue, efficiency, service).
Command and control thinking Vs System thinking
How do we think about purpose?
Defined by functional measures Vs Defined by what matters to customers
Starting point for analysis:
Current process activity Vs System response to customer demand
Method for change:
Analyse, design and tell Vs Check and learn
Use external resources Vs Use internal resources (aided by catalyst)
Managements job:
Control Vs Prediction
Result:
(If successful) Vs Learning, flexibility
incremental improvement
then stasis continuous improvement
A system view of the organisation would lead a manager to first gain an
understanding of the organisations current capability and the reasons for it (system
conditions). In other words he would know what the system is currently achieving
and why. This understanding is a prerequisite to removing things that inhibit change and
introducing the things required to manage the new system.
BPR is re-design of the system, it requires a system perspective. The best
place to start is check.

The priority is to understand the current system warts and all. In simple
terms, this means understanding what matters to customers; the organisation's current
ability to respond to those requirements; the nature and scope of the processes which
deliver that performance and the way in which the current system - rules, roles, measures
and so on - impacts process performance.
Some argue that the present system is to be obliterated, so why start with
check? The danger is that change not based on understanding can produce disastrous
consequences. The example (in box) is an extreme illustration of what is an all-too-common
phenomenon. Furthermore, understanding the current system tells you more about customer
demand; how can processes be re-designed without it in mind?
Making changes without knowing how things currently work
A maintenance organisation had grown rapidly by acquisition. Each of the
acquired companies had its own procedures and practices. Clearly there was an opportunity
to make efficiency gains by standardising procedures. On the advice of consultants, groups
of managers were brought together to re-engineer systems and procedures for the newly
integrated organisation.
The group responsible for the spares system determined that it would be
most efficient to organise nationally, using a system similar to that being operated by
one of the original companies. The decision was announced and the new system implemented.
Some unfortunate consequences followed. Managers in most of the merging companies had been
held accountable for the cost of spares held locally. These figures were still being used
to determine branch profitability and, therefore, the manager's bonus. Under the new
system, where spares were treated as a national resource, one branch manager could, in an
emergency, order a spare from another. As the cost of spares held locally effectively
counted against a manager in his bonus scheme, it soon became common practice to hold
minimal spares locally and order them as emergency items from nearby branches when
required. The additional cost associated with transportation was the immediate wasteful
consequence, but worse was to come.
To avoid losing spares to nearby branches, managers began to stop logging
some items on the national system. Quite rightly their concern was to maintain a level of
service to their customers. The practice of hiding spares resulted in two problems.
Firstly, the unreliability of the national system, and secondly the increase in the cost
of spares held throughout the organisation. In circumstances such as these, senior
managers can only respond with drastic measures. In this case they stopped managers buying
spares by reducing their authority levels. The first person to be affected was the
customer.
What matters to customers and current process performance (how well we
respond) would be the baseline against which the success of the initiative should be
measured.
From an understanding of the organisation's current capability and the
reasons for it (system conditions) the manager would be more able to act on the sources of
improvement, he would know how to act on the system. And it is not just a work system, it
is a human system.
People as the solution, not the problem
In a command and control culture, managers tend to think of performance
problems as people problems. To solve these problems they pursue motivational programmes,
development programmes and put in place a variety of people management processes (e.g.
appraisal, pay). A systems view would lead to quite different action.
Deming and Juran estimated that more than 95% of performance problems were
due to the system. The people are in the system, they are subject to the measures,
processes, information, methods, tools and so on that are in place. In every organisation
you find that people in the workplace know things about what works and what doesn't. They
are fully aware of the impact of their system's performance on customers and are often
powerless to do anything about it. If they have to work to constraints (e.g. standards,
measures) imposed by managers who know little of the work, their morale suffers.
A manager who thought of the organisation as a system would recognise the
need to develop methods for change which put the people, the future knowledge-workers, at
the forefront of the development of that knowledge. He would not value black-box
consultancy agreements, he would refuse to allow the grey-suits to conduct an analysis,
write a report and recommend strategies for change that involve more consultants. He would
appreciate that black-box consulting takes knowledge out of the system.
People are the competitive weapon. BPR often sets out to simplify
and increase the flexibility of processes. To operate such processes, you need a culture
that enables people to bring their brains to work. Not only should the solution be
cognisant of this fact but the method employed in any change will help or hinder according
to its inherent assumptions about people. Are they to be told how to work in the new
order? If so, will this and other command and control assumptions stand in the way of
effective change? For example, what measures will be used to run the new system and who
will use them? Will their use result in learning and improvement or controls which dampen
morale?
While people in the work processes do have first-hand information about
what is currently going on, they usually lack a framework or perspective within which to
organise and articulate their experience. To turn such experience into knowledge a
framework against which they can theorise and test their theories in action is required
(for example, how would sales be affected if billing enquiries ceased?). If the future
belongs to knowledge-workers, the analysis of the current system must be performed by
them.
Many managers of command and control organisations would be terrified at
the thought of workers getting involved in analysis of their organisation. They would
argue that their people wouldn't have the ability or motivation. They often fail to
recognise that what they see in their people today is the product of years in the
prevailing system. It is simpler and cleaner to engage consultants to conduct an analysis,
but if that means others developing knowledge, it is a step in the wrong direction. The
role of the consultant should be to catalyse change through giving people a different
perspective, to create knowledge in the system, not take it away.
Changes as a consequence of BPR
If we do change our systems in a way that demonstrates our belief in
people as the greatest asset, the human resource management processes will need to be
aligned to create and maintain the new order. A learning organisation needs the means and
conditions for learning.
An organisation of knowledge-workers relies on a sound infrastructure to
work in such a way as to be able to control and improve performance. Knowledge-workers
don't only work in the system, they act on it. For example, highly flexible processes
require quick decision-making with the quality of decision-making enhanced by measurement.
The right measures need to be in the right hands to take action for improvement.
Other aspects of the system are beyond the workers' control: pay,
training, development and so on are determined by policy-makers. It is critical to ensure
that such policies are contributory to a change in the system and not an impedance. The
thinking of the policy-makers needs to start from the same assumption - that the
organisation is a system. It raises profound challenges for traditional human resources
processes in organisations.
Pay
If the majority of variation in performance is governed by the system why
have differentials in pay? There is no doubt that a beginner will not be as proficient as
an experienced worker and there is a case for developing pay systems that reflect
contribution. As people learn more and contribute more, they should be paid more. Pay
policy should value contribution more than status.
Few managers appreciate the damage caused by incentive pay (see box).
Kohn(3) provides a thorough summary of the research in this field.
Some of the damage caused by incentives